Penticton is building its new fire headquarters on the site of Hall No. 2 on Dawson Avenue. Once the new building is commissioned, the current headquarters on Nanaimo Avenue will serve as a satellite station and the city’s Emergency Operations Centre. The city broke ground on Dawson Avenue on October 1. City groundbreaking announcement
The work is already showing up in the proposed 2027 tax bill. Penticton’s draft budget attributes 2.38 percentage points of its proposed 5.81 per cent property tax increase to debt payments for the new headquarters. That makes the fire hall the largest item the city identifies in its breakdown of the increase. City draft budget · OKTD’s November budget coverage
What Penticton is building on Dawson Avenue
The two-storey building is planned at about 26,300 square feet. It will bring fire administration, prevention, training and emergency response under one roof, with space for regional firefighter training. The city describes it as a post-disaster facility, meaning it is designed to remain functional after a major event. Council’s September 29 update put completion in the third quarter of 2028. City project scope · September council decision
Who is building the fire hall
Chandos Construction is the general contractor and Johnston Davidson Architecture is the architect. The city named AltaPro Electric, Falcon Engineering and Betts Electric on the electrical side, and WSP Canada, Falcon Engineering and Chapman Mechanical on the mechanical side. RJC Engineers is the structural consultant. City project team announcement
Penticton selected the main team through competitive procurement and is using integrated project delivery. The city, designers and major trades worked out the scope and target cost together before construction. For contractors tracking the job, those appointments are already made. Any further work advertised for bidding should be checked against the city’s posted opportunities for its scope and closing date. City of Penticton bid opportunities
Why the city has published different cost figures
In June, the city put the broader renewal program at $38 million, with $37 million for the Dawson Avenue headquarters and $1 million for work at Hall No. 1. In September, council endorsed the construction team’s validation report for the headquarters with a $33 million target. The June figures describe the broader budget and its allocations. The September figure is the target cost council endorsed for the headquarters project. June budget breakdown · September council decision
Residents can comment on the draft budget through December 2, 2026. Penticton Budget Talks